3.8.1 Ballistic test plates. In addition to the markings in 3.8, each ballistic test plate shall be marked
with the letters PRE for First Article test plates and ACC for Acceptance test plates. This marking
shall be impression stamped on the edge in letters 3/8 inch high or greater. Ballistic retest plates
shall be marked "R1" and "R2" respectively (see B.5.2).
3.9 Ballistic test plate information. For each lot of aluminum alloy armor a properly completed
Aluminum Armor Test Data Form (See Figure 1) shall be submitted with each ballistic test plate
that represents that particular processing lot.
3.10 Workmanship. Plate produced under this specification shall be uniform in quality and clean,
smooth and sufficiently free from buckles, blisters, hard spots, damaged ends, laminations and other
defects which may affect its use.
3.10.1 Surface and Edge Condition. The surface and edge condition of the plate shall be free of
surface cracks, edge cracks, and edge laminations as defined in the contract or purchase order (see
6.2).
3.11 Stress Corrosion Cracking Resistance. Unless otherwise specified in the contract or order (see
6.2) plate material 0.72 inch and thicker in the short transverse direction shall be resistant to stress
corrosion cracking. A minimum of 5 of the 9 specimens tested shall show no evidence of cracking
at the end of 96 hours when tested as specified in 4.7.4.
4. VERIFICATION
4.1 Classification of inspection. The inspection requirements specified herein are classified as
follows:
a. First article inspection (see 4.3).
b. Conformance inspection (see 4.4).
4.2 Lot. A lot shall consist of all plate of the same alloy; same source of molten metal representing
the ingots poured, and ordered thickness which has been processed together by the same mill
practice. Unless otherwise specified in the contract or purchase order (see 6.2), the weight of the
finished plate in the lot shall not exceed 50,000 pounds and shall be submitted for inspection as a
unit.
4.3 First article inspection. When specified in the contract or purchase order, (see 6.2) and before
production has commenced, samples of specified material shall be made available to the contracting
officer or his authorized representative for approval in accordance with 4.3.1. The approval of the
first article samples authorizes the commencement of production but does not relieve the supplier of
responsibility for compliance with all applicable provisions of this specification. The first article
samples shall be produced using the mill production practice proposed for use in production.
4.3.1 First article inspection. First article inspection except as otherwise indicated in this
specification, shall utilize the same requirements and test methods as the conformance inspection or
production acceptance inspection shown in 4.4.
4.4 Conformance inspection. Conformance inspection or production acceptance inspection shall
include the examination of 4.6 and the tests of 4.7.
6
For Parts Inquires call Parts Hangar, Inc (727) 493-0744
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business